oh but mine hasn't changed yet. how tio force them to change ? I have submitted the defect lists on Apr 5 and then Apr 24 but only about 50% completed.
[quote:a806c0b292="Wynne & Paul"]oh but mine hasn't changed yet. how tio force them to change ? I have submitted the defect lists on Apr 5 and then Apr 24 but only about 50% completed.[/quote]
So long. They always say will complete within 4 weeks. If you submitted on Apr 5 almost 4 weeks passed. Do you have any action plan? :em13: :em13: :em13:
[quote:b2cf5975c0="Wynne & Paul"]oh but mine hasn't changed yet. how tio force them to change ? I have submitted the defect lists on Apr 5 and then Apr 24 but only about 50% completed.[/quote]
I also submitted form on the same date as you status is so far so good. Around 10 days before they called me saying all defects has been settled and said that they will change the windows after 2 weeks when the windows are ready.
Re the bricks of kitchen and toilets you should call Defect Office (31651280) tell them you cannot accept the brick quality you think they NEED to change it ar. If they said "no" you can quote RC mates 's sucessful case lo.